2015-11-06 Completion of building works certificate
Completion of building works certificate More


2015-10-12 The first heating season has started

The first heating season has started.

More


2015-08-28 Acoustic and energy efficiency classes
It is confirmed acoustic and energy efficiency classes. More


2015-06-30 Elevator installation works
Elevator installation works are almost completed. More


2015-05-15 Inside walls and flooring installation works
Inside walls and flooring installation works have been started. More


2015-05-07 Facade finishing works
We have just started facade finishing works. More


2015-02-10 Facade finishing materials
We selected high-quality finishing materials: high-pressure laminate panels and clinker ceramic panels. More


2015-02-09 Window installation works
Installation works of multiple glazing, warm windows have been started. More


2015-01-28 Recreational park in the territory
Planning of the recreational park in the forest, belonging to the territory, is currently taking place. More


2014-11-04 Partitions between apartments
Masonry works of high thermal and acoustic class partitions between apartments are in process. More


2014-10-24 Masonry works
Works of masonry walls of a building "A" have been started. More


2014-09-25 Frame construction
Frame construction works of a building "A" have been started. More


2014-09-23 Ground floor
Ground floor works are finished. More


2014-07-17 Foundation works
Foundation works have been started. More


2014-06-17 Preparatory construction work
Preparatory construction work have been already started. More


2014-06-17 The building permit has been obtained
JSC “Palanga City” has been authorized to build four new residential buildings at the address Žiogų Street 6, Palanga. More